Payment Plan

:: Construction Linked Plan ::
(A)
At the time of booking / allotment
7.5% of BSP
(B)
Within 60 days (2 months) of booking
7.5% of BSP + 25% of EDC / IDC
(C)
Within 120 days (4 months) or commencement of Excavation*
7.5% of BSP + 25% of EDC / IDC
(D)
Within 180 days (6 months) or Commencement of Basement*
7.5% of BSP + 25% of EDC / IDC
(E)
Within 240 days (8 monts) or Commencement of 3rd floor slab*
7.5% of BSP + 25% of EDC / IDC
(F)
Within 360 days (12 months) or Commencement of 6th floor slab*
7.5% of BSP + 20% Amenities charges
(G)
Within 450 days (1 year 3 months) or Commencement of 9th floor slab*
7.5% of BSP
(H)
Within 540 days (1 year 6 months) or Commencement of 12th floor slab*
7.5%of BSP + 20% Amenities Charges
(I)
Within 630 days (1 year 9 months) or Commencement of 18th floor slab*
7.5% of total cost
(J)
Within 720 days (2 years) or Commencement of masonry work
7.5% of BSP + 20% Amenities Charges
(K)
Within 810 days (2 years 3 months) or Commencement of 27th floor slab*
7.5% of Total cost
(L)
Within 900 days (2 years 6 months) or Commencement of Last floor slab*
7.5% of BSP + 20% Amenities Charges
(M)
Within 990 days (2 years 9 months) or Commencement of flooring / services
5% of BSP + 20% Amenities Charges
(N)
On offer of Possession (3 years)* whichever is later*
5% of BSP, *IFMS+*REG. & Admin. charges
:: Down Payment Plan ::
(A)
10% Rebate on BSP
As Applicable
(B)
90% within 60 days + 100% Amenities Charges
As Applicable
:: Additional Charges ::
(A)
Amenities Charges
70 Lacs
(B)
*EDC (External Development Charges)
As applicable
(C)
*IDC (Infrastructure Development Charges)
As applicable
:: Operational & Facility Management Charges ::
(A)
Capital Replacement Fund
As fixed from time to time
(B)
Interest Free O & FM Security Deposit
Rs 50.00 per sq. ft.
(C)
O & FM Charges
As fixed from time to time
(D)
Transfer Charges
As applicable